Showing posts with label belt bucket elevator. Show all posts
Showing posts with label belt bucket elevator. Show all posts

Tuesday, December 15, 2015

Mainly Factors about Model Selection of Bucket Elevator

As common used lifting equipment, selection of bucket elevator is effected by many factors, wrong model will give customers endless troubles. Generally, model selection of bucket elevator depends on the following factors.
1. Material shape: powder, granular or small lump material.
2. Physical property: adsorbability or viscosity, and moisture content.
3. Proportion of material: common bucket elevator parameters are designed and calculated according to the materials which mass density under 1.6. While large proportion of materials are according to tensile strength of traction and drive part.
4. Unit conveying capacity:
Generally speaking, shape of material directly determines the discharging method. It is common practice that powder materials use centrifugal discharge and gravity discharge for lump materials. In addition, different charge method determines the different type of bucket, centrifugal discharge always use shallow or arc bucket, while deep bucket for gravity discharge. The unit conveying capacity of bucket elevator is different as its different bucket type. The conveying capacity of bucket elevator is a comprehensive parameter that depends on bucket type, speed, proportion of material, property of material and number of bucket. Selection process is as follows: proportion of material, property of material, discharging method, bucket type, conveying capacity and the model.
bucket elevator supplier
 Bucket Elevator

Friday, December 11, 2015

How to Solve the Problem of Hopper Belt Slipping?

1) Bucket elevator uses the friction between the hopper belt and the head wheel drive shaft to lifting material. If the hopper belt strength is not enough the hopper belt will slip. At this time, you should shut down the machine immediately and adjust the take-up unit to tension the hopper belt. If the take-up unit can’t make the hopper belt fully tension, this shows that the take-up unit work distance is too short, you should re-adjusted it.

Solution: Open the joint of hopper belt, adjust the take-up unit in on the tail wheel to the highest position, put the hopper belt via head of elevator, threading head wheel and tail wheel and connected tail and head well, then the hopper belt will keep the tension but not fully tension state. In this case adjustment spindle of the take-up unit work distance should not less than 50% of the whole work distance.
Bucket elevator
2) When bucket elevator is overloading, the resistance torque will be increased and make the hopper belt slipping. In this case, you should reduce the feeding material and try to feeding uniformly. If it didn’t work, then the possible reason is there is too many material piled up in the base or hopper locked by the piled up material. At this time, you should shut down the machine and begin troubleshooting process.

3)
 If the inner surface of head drive shaft and hopper belt is too smooth, then the friction between them will be reduced, which will caused the hopper belt slipping. In this case, you can spread a thin layer on their inner surface to increase the friction.

4)
 The bearing of head and tail wheel occurs inefficient rotating will increased resistance torque and result in the hopper belt slipping. At this time, you can open, wash, oiling the bearing or change the bearing.
Bucket elevator

Thursday, December 10, 2015

The Right Way to Install the Bucket Elevator

1.Before the installation you should fixed base firstly, base should be fixed on the reliable basis, then connected to the machine base barrel step by step, finally connecting the handpiece and installing gear motor.

bucket-elevator-motor
Bucket Elevator Bearing
2.After installation and alignment the whole machinery, you should make sure that barrels across the floor and must be fixed with the floor, if it has attachment then you should install bearing housing bracket to prevent the whole machine tilt and displacement.
bottom-section
Bottom Section


3.In order to ensure seal the barrels connection allows to use the barrel gasket.
bucket elevator inspection window
Inspection Window
4.Hopper should installed on the hopper belt as required, hopper belt with hopper were placed from both ends of the handpiece. When you install the hopper belt, you should raise the bottom wheel to the highest position.
middle-section
Middle Section
5.Aligning the head wheel shaft to horizontal, and make the head and tail wheel shaft are located within a unified vertical tail plane.
6.Bucket elevator is one kind of vertical transportation equipment, head wheel, bottom wheel, and barrels should be sought in the same vertical line; the deviation per meter length should not more than 2 mm, the accumulation of deviation should not more than 8 mm.

bucket elevator manufacturer
Bucket Elevator
7.Hopper mounted in the elevator, there should not happen deviation result in the housing crash 
8.The hopper belt tensioning device should ensure the necessary uniform tension during normal work.
9.After finish the elevator installation, you should filled every lubrication part with oil lubrication, before the loading test and put into production you should make sure that the no-load test can normal work.

Wednesday, November 18, 2015

What You Should Know about the Bucket Elevator When Installing

What You Should Know about the Bucket Elevator When Installing

Bucket elevator is a new equipment which is used for lifting materials vertically.So it can be widely used in mining,cement,power plant,metallurgy,chemical,etc..But how to install the bucket elevator safely,the notices are as follows:

1.Pay attention to the casing installation of the bucket elevator

When installing the bucket elevator,you should install the lower parts and fixed anchor bolt first,and then install the middle casing and upper casing.During the installation,high altitude bucket elevator in which part of the machine and the appropriate position of the upper casing should together with its neighboring buildings in order to increase its stability.After installing the casing successfully,you should adjust the perpendicularity correctly.


bottom-section

2.Pay attention to the chain and hopper installation of the bucket elevator

Hopper is connected with U screw,which is chain joint and fixed part of a hopper.The nuts of the U screw must be tightened and reliable locking.After installing,you should adjust them with a proper tension.

3.Adding appropriate amount of oil 

Reducer should use the industrial gear oil lubrication.
Within the bearing seat should use the sodium calcium base or butter.

bucket elevator manufacture

Tuesday, November 3, 2015

How to Install the Asbestos Tape in the Bucket Elevator?

How to Install the Asbestos Tape in the Bucket Elevator?

In the process of the installation of the bucket elevator,in order to prevent the leakage of dust, pollute the environment,our engineer always using the asbestos tape in the bucket elevator.Here we will introduce the detailed information as follows.

asbestos-tape

Why the asbestos tape has such good sealing?That's mostly because the asbestos tape is woven with high quality stone cotton yarn.Asbestos tape is suitable for various thermal equipment for heat preservation, heat insulation material or processed into other asbestos products.

bucket elevator
A good sealing plays an important role in the installation quality of the bucket elevator.  Asbestos Tape is the best choice of sealing material, which is installed on the casing flange joints.What you should pay attention is that you should put the asbestos tape into the interface before connecting flange, and then connecting the bolts.

asbestos-tape-of-bucket-elevator

Thursday, August 6, 2015

Efficient Bucket Elevator Transport for Bulk Materials

1. What is the conveying material and its physical characteristics? such as bulk density, feeding size, temperature, mositure content etc.    
2. What is the processing capacity of the elevator?    
3. What is the lifting height of the elevator (distance between inlet and outlet)? 
Why we choose this bucket elevator ?
       General rubber belt is suitable for material temperature less than 80 ℃ ,heat-resisting rubber belt is suitable for material temperature less than 120 ℃. Max. Lifting height 80m , Capacity is approx. 2080 m3/h.
      THG bucket elevator adopts high strength link chain as the traction component , draw our type feeding material , centrifugal or hybrid discharge material . Material temperature is less than 250℃. Max. lifting height 75m , Capacity is approx.1800m3/h. 
       Hopper scoops up materials from the stone bucket below, then is lifted to the top with the conveyor belt or chain, and next it is downward rolled over bypass the wheel on the top and the materials are dumped into the accept slot now by bucket chain or hoist conveyor, and the whole process is over. The driving band of bucket elevator with driver is commonly made of rubber, and it is installed below or above the drive roller and the divert roller. The chain-drive bucket elevator is generally equipped with two parallel transmission chain, on which above or below is a drive sprocket and a divert sprocket. Continuous Chain or Belt Bucket Elevator for Cement are generally equipped with chassis to prevent the dust flying into the bucket elevator.
       At the same time, TDG/THG bucket elevator with Sh type buckets are widely used in transporting dry , loose and good fluidity powder , granular , block material ; with Zh type buckets are widely used in transporting moist , caking and bad fluidity powder , granular material .
Henan Mining Machinery Co.Ltd is a mining machinery manufacturer from China supplying kinds of vibrating screen,belt conveyor(conveyor belt), bucket elevator,screw conveyor,scraper conveyor and spare parts.The machines are widely used in mine, metallurgy, chemical industry, cement, petroleum etc.the business include research,design, manufacture and export.so if you have some demand please contact us freely,I would be glad.
Our company has experienced engineers who can help you install equipment with appropriate directions on site as well as the after-sale service.
Tel: +86 373 579 9198
Fax: +86 373 507 1699
Skype:pkmachinery09
Address: 289 Yellow River Road, Xinxiang City, Henan Province, China

Saturday, August 1, 2015

Belt Bucket Elevator Transport Shape Matherial for Glass

Belt bucket elevator is designed for transporting vertically for granular, powder and small block of grinding suction smaller disperses the shape material. It adopts belt as the traction component , can reach to max.40 meters . Capacity could be approx. 4~238m3/h .
The bucket is filled with material and is conveyed to the head terminal, and then the material is thrown from the outlet under the action of centrifugal force according to the parabolic design. The driving device drives pulley to operate the bucket belt in circular motion from bottom to up. After discharging, the empty bucket is back to the boot by conveying and be filled again, and then lifted up to do parabolic motion such repeated cycle. The material is lifted from bottom to the top to the specified height to reach conveying vertically.
Features&Applications
1.Smooth transmission – no impact caused due to the traction member
2.Less noise pollution – good sealing sound system
3.Greater conveying speed due to smooth transmission
4.Longer life span
5.Low cost compared with other conveyor for powder materials.
The vertical belt bucket elevator is widely used in mining , metallurgy , chemicals , power plant , agriculture and quarry etc industries for handling products such as cement, raw meal, alumina, coke, foundry sand, wood chips and other materials.
A general belt bucket elevatorinspection every six months, mainly on the hopper and belt tightening bolt joints check processing, tightening or replacing bolts. Each belt test once a year to confirm the age of the plastic surface of the belt and the belt strength. Adjust the level of the cylinder head and tail roller to correct the belt deviation. If the deviation is caused by drum plastic surface wear, re-roll the car hanging plastic and rubber surfaces. The rear bearing need to regularly check. Generally, after a long time usage, it will cause wear on slip ring seal. This can cause the bearing oil drip and caused bearing damage. Generally, a good slip ring seal can be used for many years.
 If you want to know more information about the production of PK machinery,please pay a close attention to anneguo@linkedin.Thank you!                     E-mail:anneguo329@gmail.com  Skype:pkmachinery09
Henan Pingyuan Mining Machinery Co., Ltd is the most professional manufacturer of Belt conveyor, and Vibrating screen, Bucket elevator, Screw conveyor, Scraper conveyor using the world's most advanced technology, we are willing to serve every company to meet your custom needs. Our goal is "be the future global leader of mining machinery industry". Have any questions, please contact us without any hesitation.
Website:www.pkmachinery.com    
E-mail: info@pkmachinery.com
Tel: +86 373 579 9188
Fax: +86 373 507 1699